Rural electric cooperative
Cooperative FTTH Backbone Expansion in Berlin
For a North Country electric cooperative near Berlin, we placed 68 miles of backbone and distribution to pass 1,142 homes. Average splice loss hit 0.05 dB, and the XGS-PON-ready plant accepted on first submission.
The challenge
What drives cost here is pole access and rock on this fiber-to-the-home (FTTH) build, not mileage. The Berlin system follows the Androscoggin River valley toward the Mahoosuc foothills. Shallow granite ledge and boulder till sit beside narrow New Hampshire Department of Transportation corridors on Routes 16, 110, and 16B. Most miles had to ride aging joint-use poles needing Eversource make-ready before lashing. Broadband Equity, Access, and Deployment (BEAD)-eligible hollows toward Milan and Dummer lacked resilient backhaul.
What limits schedule is winter and live power. Ice loading adds sag, freeze-thaw heaves Success Pond Road, and snow arrives early above 1,500 feet. The cooperative could not de-energize long feeders during heating season, so outages needed short windows. The design required 68 miles and about 1,100 passings. Budgets stayed tight enough for future XGS-PON service over a passive optical network (PON) without rebuild.
Our solution
We placed a mostly aerial build with short underground at rock and river crossings. A six-person crew walked each pole line, sequenced Berlin and NHDOT permits, and cleared make-ready span by span. We lashed 144-count backbone to new strand and 48-count laterals to existing strand. Around Cates Hill and Jericho Mountain State Park approaches, we cut rock-saw slots and bored horizontal directional drilling (HDD) shots under culverts.
Trailers with snow control held splice averages at 0.05 dB, with no event over 0.10 dB. Supervisor Dawn Hartman (FOA CFOS/S) proved each leg with Tier 1 tests using an optical loss test set (OLTS) per TIA-526-7-A. Tier 2 OTDR (optical time-domain reflectometer) traces at 1310/1550 nm backed readings, with .sor, PDF, splice maps, and KMZ in five days. Send pole sheets or route KMZ for a budgetary number, schedule window, and assumptions within one business day.
Coos County winter work shaped this Berlin build. Ledge and frost called for careful rural FTTH backbone placement and weather-tight core and drop splicing. It reflects our support for co-ops and municipal light plants across the North Country. Planners in the Berlin area can send mile counts and address lists. They receive a budgetary number, schedule window, and assumptions within one business day.
More projects
Similar recent work

Ice Storm Emergency Restoration in North Conway
Regional ISP lost nine miles of aerial plant on Routes 16 and 302. We relit the core ring in 18 hours and rebuilt 600+ splices to heavy-ice spec in three weeks.

Downtown Municipal Conduit Backbone in Concord
For Concord's broadband office, we designed and placed 22 miles of backbone and microduct through downtown and Penacook. The 288-count open-access plant passed testing and left Main Street brickwork intact.

Garden Apartment Fiber Build in Rochester
We delivered PON-ready fiber to 180 units across three buildings in Rochester, pairing provider-neutral distribution with clean telecom rooms for fast turn-up.

Launch a project
Get a Fixed Fiber Price
Send drawings or route Google Earth map file (KMZ). Get itemized price, schedule window and exclusions within one business day.
Expect a planning estimate within one business day.