NH Contractor License #NH-889348 · Bonded & insuredAll 10 counties
Fiber Optics New Hampshire
Night emergency fiber restoration crew at a cut site

Regional ISP

Ice Storm Emergency Restoration in North Conway

Regional ISP lost nine miles of aerial plant on Routes 16 and 302. We relit the core ring in 18 hours and rebuilt 600+ splices to heavy-ice spec in three weeks.

North Conway, NHISPs & Telecom Carriers3 weeks
18 hoursto relight core ring on temporary spans
9 milesaerial plant rebuilt to heavy-ice spec
600+emergency fusion splices averaging 0.05 dB bidirectional optical time-domain reflectometer (OTDR) verified
47break points cleared with updated pole maps and baselines

The challenge

Emergency fiber restoration began after a February nor'easter iced the Mount Washington Valley from Glen to Intervale. Nine miles of ADSS (All-Dielectric Self-Supporting) cable and messenger-lashed distribution fell along Routes 16 and 302 inside the White Mountain National Forest. The ISP lost backhaul to North Conway Village, Bartlett lodges and ski-area systems during peak vacation week. NHDOT kept Kancamagus shoulders closed for plows and tree crews, limiting access to tracked carriers.

Drifted pull-offs and subzero cold forced splicing from heated tents, with spans reachable only on snowshoes in places. Forest Service and scenic-byway rules barred off-corridor anchors along the Routes 16 and 302 corridor. Hotels and rentals needed check-in systems back before the weekend rush. The rebuild had to raise ice loading for the next storm, not just replace like for like.

Our solution

Our crew staged in Conway within six hours and patrolled with the ISP to mark 47 break points. We hung temporary pre-connectorized spans to relight the core ring overnight while NHDOT permits and Forest Service access cleared. A six-person team then rebuilt with heavy-ice ADSS, taller slack loops and tree-wire clearance on Crawford Notch approaches to shed loading. Night lane flagging kept Route 16 open for plows and ski shuttles during pulls and tensioning.

Lead splicer Rafael Brock (FOA CFOT) ran 600+ fusion splices from heated tents at Echo Lake and Glen. He averaged 0.05 dB with none over 0.10 dB. Each span passed bidirectional OTDR (optical time-domain reflectometer) testing at 1310/1550 nm per TIA-526-7-A, with Tier 1 insertion-loss inside TIA-568.3-D limits. All work followed National Electrical Safety Code (NESC) clearances and OSHA 29 CFR 1926. It included .sor files, pole maps, baselines and two-year workmanship warranty. For outages call (603) 555-1131, text photos with addresses for a callback in 15 minutes and a dispatch window.

The February nor'easter dropped spans, ice-loaded poles and downed closures along Routes 16 and 302. This job combined overnight storm damage repair with emergency core ring splicing. It reflects our carrier backbone restoration support through the White Mountains. Carriers serving the North Conway region can call dispatch first with damage locations for an on-site window and restoration plan within hours.

More projects

Similar recent work

BerlinElectric Utilities & Cooperatives22 weeks

Cooperative FTTH Backbone Expansion in Berlin

For a North Country electric cooperative near Berlin, we placed 68 miles of backbone and distribution to pass 1,142 homes. Average splice loss hit 0.05 dB, and the XGS-PON-ready plant accepted on first submission.

LaconiaTransportation & ITS7 weeks, including overnight splicing windows

Signal Corridor Fiber Design in Laconia

We designed 8.5 miles of traffic-signal fiber in Laconia and spliced 48-count trunks under overnight closures. Our work gave public works a documented intelligent transportation systems (ITS) path.

LebanonEducation & Campuses14 weeks

Campus DAS Fiber Backhaul in Lebanon

For a private university group in Lebanon, we built OS2 backhaul. It reaches 12 distributed antenna system (DAS) and small-cell nodes across the Upper Valley complex. Signal gaps closed in halls, garages, and labs with headroom for two more carriers.

Launch a project

Get a Fixed Fiber Price

Send drawings or route Google Earth map file (KMZ). Get itemized price, schedule window and exclusions within one business day.

Expect a planning estimate within one business day.

24/7 dispatch and restoration(603) 555-1131Use (603) 555-1131 24/7 and get a reply when fiber goes dark. Crews based in Nashua, Manchester and Portsmouth lay temporary cable to get circuits up, then splice the permanent repair and test it again.