Quick answer
What is make-ready? It is the work to clear space on utility poles for new fiber. Crews move wires, replace short poles or add height. One-Touch Make-Ready lets one approved crew do simple transfers in the communications space to cut wait time.
Poles across New Hampshire carry power, phone and cable in tight vertical space. Our aerial fiber crew surveys each pole, flags clearance faults and sequences transfers. New strands can ride without NESC violations or storm risk.
You will learn simple versus One-Touch Make-Ready, what an attachment application needs, and when to lash new strand or overlash existing bundle. Cost drivers reflect granite ledge, ice loading and short rural pole lines from Rochester to the North Country.
What Is Make-Ready in Plain Terms?
Make-ready is the field work that creates a safe attachment slot for new fiber. A make-ready (pole preparation for new attachments) survey measures existing wire heights. It checks pole condition and National Electrical Safety Code (NESC) clearances over roads and driveways. Crews then shift telecom wires, raise drops, replace rotted poles or set taller poles where height falls short. Only after corrections can lashing begin.
New Hampshire poles often show low telecom clearance after ice years and repeated resurfacing. Eversource, Liberty, Unitil and Consolidated Communications own many joint-use poles, with NHEC poles common in co-op territory. A 40-home side street may need five to fifteen poles touched. Expect photos, height sheets and a stamped correction list for each pole before scheduling.
One-Touch Make-Ready vs Simple Make-Ready: What Changes?
Simple make-ready follows the classic sequence with each attacher moving its own wires. The new attacher applies, the pole owner surveys, notices go to existing attachers, and each company schedules its own transfer. Timelines stretch when crews must return for snow, outage work or short daylight in January. Rural routes with three attachers can take months.
OTMR (One-Touch Make-Ready) allows a single approved contractor to perform simple transfers inside the communications space. Complex work above the communications worker safety zone and any electric-space work stays with the owner. FCC OTMR rules set notice and schedule windows, while NH Public Utilities Commission practice and owner tariffs shape local forms. Ask your engineered permit package source to mark simple versus complex poles on the plan set.
What Does a Pole Attachment Application Include in New Hampshire?
A pole attachment application tells the owner where you want to ride and what load you add. Packages include a route map, pole numbers, proposed attachment height, cable size and weight. They also list strand diameter, span lengths and calculated tension under ice and wind. NESC Grade B is common for crossings over state routes. NHDOT occupancy and municipal street-opening permits ride alongside the pole filing.
Owners check pole strength, guying and clearance to power neutral. Granite backfill and shallow ledge around Suncook, South Hooksett and Somersworth can limit new anchors, so show guy alternatives. Include traffic control notes per MUTCD for Route 101, Route 16 and downtown Portsmouth work. Clean filings with Google Earth map file (KMZ), photos and load notes move faster than bare pole lists. If grant timing matters, review BEAD rules for Granite State builders early in design.
Strand and Lash vs Overlash: Which Method Fits?
Strand and lash sets a new steel messenger and lashes fiber to it with wire. Crews tension the strand to control sag under New Hampshire ice loading, then lash 48- to 144-count standard loose-tube cable. New strand fits where no usable messenger exists or where bundle weight would overload the pole. It costs more but gives clean tension and future lash room.
Overlash straps new cable to an existing lashed bundle without setting new strand. It saves time and avoids extra drilling where poles are crowded near Keene and Laconia. Limits include bundle diameter, weight, clearance loss and owner approval for third-party bundles. Study PON hub and terminal layouts to set bundle size for future drops. Field supervisor Jonah Kinney (FOA CFOS/T) load-checks spans over 175 feet before approving overlash.
Who Pays for Make-Ready and What Drives Cost in New Hampshire?
The new attacher usually pays for surveys and the corrections its attachment triggers. If a pole is already out of clearance, tariffs and prior agreements decide cost shares between owner and attachers. Pole replacement, taller poles, new anchors in ledge, and traffic control set the high tickets. Short spans help, while long rural spans with rot raise unit cost fast.
Granite State drivers include rock anchors, short replacement poles flown by crane on narrow Class VI roads, and winter standby. A recent 62-pole correction near Dover cost less per pole than a 22-pole rebuild near Berlin where six poles needed replacement. Broadband Equity, Access, and Deployment (BEAD) budgets should carry contingency for replacements found after boring or potholing. Get itemized pole-by-pole pricing before you sign construction.
How Do You Keep an Aerial Build Moving Through Make-Ready?
Sequencing beats speed once notices go out. Survey all poles first, then group simple transfers by town so one crew clears ten to twenty poles per visit. Hold complex electric-space poles on a parallel track with the owner. Weekly photo updates prevent re-surveys after storms shift wires or ice drops a neutral. Crews stage reels in Nashua, Manchester and Concord yards to cut haul time.
Documentation closes the loop for power and co-op joint owners that audit attachments each year. Deliver corrected height sheets, before-and-after photos, as-builts in KMZ and PDF, plus optical time-domain reflectometer (OTDR) and optical loss test set (OLTS) results after lashing. A workmanship warranty of 2 years backs installed plant work. Send pole numbers and a route KMZ for a per-pole estimate and schedule window.
| Step | Simple Make-Ready | One-Touch Make-Ready |
|---|---|---|
| Who moves wires | Each attacher moves its own | One approved crew moves simple transfers |
| Where allowed | All poles | Only simple work in communications space |
| Electric-space work | Owner schedules | Owner still performs |
| Typical speed | Slower with multiple visits | Faster for simple routes |
| Paper trail | Notices per attacher | Consolidated notices with photos |
Key takeaways
- Make-ready clears a code-safe slot before fiber can attach.
- OTMR combines simple transfers under one approved crew.
- Applications need maps, loads, heights and permit notes.
- New strand adds capacity; overlash saves time where allowed.