City broadband office
Downtown Municipal Conduit Backbone in Concord
For Concord's broadband office, we designed and placed 22 miles of backbone and microduct through downtown and Penacook. The 288-count open-access plant passed testing and left Main Street brickwork intact.
The challenge
What the city buys is a municipal fiber backbone without street damage. Concord wanted city-owned fiber linking City Hall, the State Library corridor, schools, and the Penacook business district. Newly rebuilt Main Street brick could not be cut, and ledge sits inches below North Main and Storrs Street. Merrimack River floodplain vaults flood each spring, which sets vault and splice-case heights.
How long and how disruptive depends on permits and working hours. NHDOT, City Engineering, and historic review govern cuts across Loudon Road and the downtown historic district. The design had to support Broadband Equity, Access, and Deployment (BEAD) records and leases from the South End to the Heights. Work had to keep state offices and hospital affiliates open. It allowed no daytime Main Street closures and no hits on legacy steam or Eversource duct.
Our solution
We mapped 22 miles of backbone and microduct with two Merrimack crossings and POPs for lease. A seven-person crew sequenced NHDOT and city permits for nights under Loudon Road and Storrs Street. We used horizontal directional drilling (HDD) in soil, rock slots in ledge, and reused Gas Street conduit to spare brick. Vacuum excavation plus GPR (ground-penetrating radar) cleared steam, water, and power before weekend bores.
Registered Communications Distribution Designer (RCDD) Mitch Godwin led eight installers placing high-density polyethylene (HDPE) and 288-count backbone and splicing hub drops. Tier 1 tests with an optical loss test set (OLTS) per TIA-526-7-A passed at 0.04 dB against a 0.10 dB limit. Tier 2 OTDR (optical time-domain reflectometer) traces at 1310/1550 nm backed readings, filed as .sor and PDF with DWG/KMZ in four days. Work ran under NH Contractor License #NH-889348 bonded and insured; send drawings for price and window in one business day.
Downtown Concord property owners needed a shared path for growth without repeated street cuts. The city paired open-access route and permit design with microduct and vault placement to Penacook. It shows our city-owned broadband foundation work with clean records for future drops. Officials in the Concord area can send corridor maps and site lists. They receive a budgetary number, schedule window, and assumptions within one business day.
More projects
Similar recent work

Hospital Campus Fiber Ring in Manchester
Regional hospital network in Manchester received a 12-mile diverse fiber ring linking three buildings across two Merrimack crossings. Failover verified under 50 ms with zero clinical downtime.

Cooperative FTTH Backbone Expansion in Berlin
For a North Country electric cooperative near Berlin, we placed 68 miles of backbone and distribution to pass 1,142 homes. Average splice loss hit 0.05 dB, and the XGS-PON-ready plant accepted on first submission.

Signal Corridor Fiber Design in Laconia
We designed 8.5 miles of traffic-signal fiber in Laconia and spliced 48-count trunks under overnight closures. Our work gave public works a documented intelligent transportation systems (ITS) path.

Launch a project
Get a Fixed Fiber Price
Send drawings or route Google Earth map file (KMZ). Get itemized price, schedule window and exclusions within one business day.
Expect a planning estimate within one business day.